Question: Given the following data: Activity Predecessor Duration (days) a - 10 b - 15 c a 17 d b 5 e b 4 f c
Given the following data:
| Activity | Predecessor | Duration (days) |
| a | - | 10 |
| b | - | 15 |
| c | a | 17 |
| d | b | 5 |
| e | b | 4 |
| f | c | 15 |
| g | d | 7 |
| h | e | 8 |
| i | f | 12 |
| j | g,h,i | 10 |
Required:
Draw the network and calculate the Critical Path. (10 marks )