2.1 Given the following data

Activity Predecessor Duration (days)
a - 10
b - 15
c a 17
d b 5
e b 4
f c 15
g d 7
h e 8
i f 12
j g,h,i 10

Draw the network and calculate the Critical path. (10)

2.2 South Africa celebrates Womens Day on the 9th August. The local government has contracted you to plan the 2020 celebration. Client specifications are as follows:

Estimated no. of delegates 5000
Must include a lunch meal
Must include 1 soft - drink per delegate
Must include a program for the day
Budget amount 1 650 000

Prepare a: 2.2.1 Gant Chart (a minimum of 10 activities) (6)

2.2.2 Construct a Work Breakdown Structure (graphical format) (9)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!