Question: Question 2 2.1 Given the following data Activity Predecessor Duration (days) a - 10 b - 15 c a 17 d b 5 e b
Question 2
2.1 Given the following data
| Activity | Predecessor | Duration (days) |
| a | - | 10 |
| b | - | 15 |
| c | a | 17 |
| d | b | 5 |
| e | b | 4 |
| f | c | 15 |
| g | d | 7 |
| h | e | 8 |
| i | f | 12 |
| j | g,h,i | 10 |
Draw the network and calculate the Critical path. (10)
2.2 South Africa celebrates Womens Day on the 9th August. The local government has contracted you to plan the 2020 celebration. Client specifications are as follows:
| Estimated no. of delegates | 5000 |
| Must include a lunch meal | |
| Must include 1 soft - drink per delegate | |
| Must include a program for the day | |
| Budget amount | 1 650 000 |
Prepare a: 2.2.1 Gant Chart (a minimum of 10 activities) (6)
2.2.2 Construct a Work Breakdown Structure (graphical format) (9)
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts