Question: please help! A - 10 B - 6 C - 2 D - 2 E - 4 F - 6 G - 8 This exercise
please help!
This exercise contains only parts b, c, and d b) The critical activities for the leadership training program development project are A-E-G c) The project length for the leadership training program development project days. Roger Ginde is developing a program in supply chain management certification for managers. Ginde has isted a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table Help me solve this Video Part 2 of Get more help. Activity Immediate Predecessor(s) Time (days) 10 Point 0 of 3 4 6 8 Clear all A - 10
B - 6
C - 2
D - 2
E - 4
F - 6
G - 8