Question: Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before
Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table:
| Activity | Immediate Predecessor(s) | Time (days) |
| A | 10 | |
| B | 6 | |
| C | 2 | |
| D | B | 2 |
| E | A, D | 5 |
| F | C | 5 |
| G | E, F | 8 |
This exercise contains only parts b, c, and d.
b) The critical activities for the leadership training program development project are?
-C-F-G
-B-D-E-G
-A-E-G
C. The project length for the leadership training program development project=____ days.
D. Slack time for each of the activties is
Activity Slack time
A _____
B _____
C ______
D ______
E _______
F _______
G _______
Step by Step Solution
There are 3 Steps involved in it