Question: please help Due Wed 10/28/20 Jsing the priority list T4, T7, T1, T3, T6, T2, Ts, schedule the project below with two processors. T1 (3)
please help

Due Wed 10/28/20 Jsing the priority list T4, T7, T1, T3, T6, T2, Ts, schedule the project below with two processors. T1 (3) T4 (5) T6 (12) End T2 (10) T5 (9) T7 (8) T3 (7) List the task numbers of the tasks processor one works on, in order. For example, if they work on TI then T4 then T7, enter: 1,4,7. Ignore idle time