Question: please help Using the priority list T3, T7, T2, T9, T4, T1, T8, T., T5, schedule the project below with two processors. Task Tasks that
please help
Using the priority list T3, T7, T2, T9, T4, T1, T8, T., T5, schedule the project below with two processors. Task Tasks that must be completed first T1 Time Required 2 5 6 7 T2 T3 T4 T5 T6 T7 T8 T9 971562 T1 T2, T3 T3 T4, T5 T4, T5, T6 T6 Task 7 is done by Select an answer v starting at time Task 9 is done by Select an answer starting at time The finishing time for the schedule is