Question: 9. Given the following network project : Activity Time (days) Total cost ($) IP A 2 1,000 - B 3 3,000 A C 4 1,000
| 9. Given the following network project: | |||||||
| Activity | Time (days) | Total cost ($) | IP | ||||
| A | 2 | 1,000 | - | ||||
| B | 3 | 3,000 | A | ||||
| C | 4 | 1,000 | A | ||||
| D | 1 | 2,000 | A | ||||
| E | 5 | 8,000 | B | ||||
| F | 6 | 6,000 | C, D | ||||
| G | 3 | 9,000 | E | ||||
| H | 4 | 6,000 | E, F | ||||
| I | 3 | 3,000 | G, H | ||||
| J | 8 | 8,000 | I | ||||
| a. Develop the network diagram. | |||||||
| b. Determine the critical time, path(s), and total cost. | |||||||
| c. Construct a cost-time graphic. | |||||||
| d. What is the impact on the critical time if Activity B is increased by 2 days? | |||||||