Question: please help me in this Question 5 (1 point) The following list represents CPM network of a project. Crash time Normal cost 10 Normal time

please help me in this
please help me in this Question 5 (1 point) The
Question 5 (1 point) The following list represents CPM network of a project. Crash time Normal cost 10 Normal time Activity Crash cost Predecessor (day) (days) A 8 6 $1,000 $1,600 B 7 $2,000 $2,600 5 4 $500 $1,000 A D 9 7 $4,000 $4,200 A,B E 2 1 $3,000 $4,000 Which activity should be crashed first to cut one day from the project's duration; how much is added to project cost? on CD B: $200 E: $1000 D: $100 C; $100