Question: Consider a project with the following information. Activity Immediate predecessors Normal time Crash time 10 8 B A 12 11 A 11 10 D 8

Consider a project with the following
Consider a project with the following information. Activity Immediate predecessors Normal time Crash time 10 8 B A 12 11 A 11 10 D 8 E B, C 5 3 What is the total cost of crashing the project by 1 time unit(s)? Crash cost per period $160 $300 $150 $220 $250 26