| Task | Duration | Predecessor | Successor |
| start | 0 | A,C,F | |
| A | 43 | start | B,D,E |
| B | 40 | A | G,H |
| C | 22 | start | I |
| D | 27 | A | G |
| E | 32 | A | I |
| F | 27 | start | H |
| G | 40 | B,D | I |
| H | 40 | B,F | I |
| I | 58 | C,E,G,H | J |
| J | 34 | I | end |
| end | 0 | J |