Question: Please help on AON (Activity on Node) Network and find the critical path. Task Duration Predecessor Successor start 0 A,C,F A 43 start B,D,E B

Please help on AON (Activity on Node) Network and find the critical path.

Task Duration Predecessor Successor
start 0 A,C,F
A 43 start B,D,E
B 40 A G,H
C 22 start I
D 27 A G
E 32 A I
F 27 start H
G 40 B,D I
H 40 B,F I
I 58 C,E,G,H J
J 34 I end
end 0 J