Question: please help Using the priority list T1, T3, T4, T7, T6, T2, T5, schedule the project below with two processors. T1 (2) T4 (5) T6

please help

please help Using the priority list T1, T3, T4, T7, T6, T2,

Using the priority list T1, T3, T4, T7, T6, T2, T5, schedule the project below with two processors. T1 (2) T4 (5) T6 (7) End T2 (8) T5 (10) T7 (4) T3 (6) Q List the task numbers of the tasks processor one works on, in order. For example, if they work on T1 then T4 then T7, enter: 1,4,7. Ignore idle time