Question: Using the priority list T2, T4, T5, Tg, T6, T1, T3, To, T7, schedule the project below with two processors. Task Time Required Tasks that

Using the priority list T2, T4, T5, Tg, T6, T1, T3, To, T7, schedule the project below with two processors. Task Time Required Tasks that must be completed first T1 3 T2 4 T3 10 9 T1 T5 3 T1, T2 T6 3 T3 T7 12 T5 T8 4 T4 T9 7 T6 Task 7 is done by Processor 2 starting at time Task 9 is done by Processor 1 starting at time The finishing time for the schedule is