Question: Please interpret....Earned Value Cost Indicators: Cost Performance Index Task Name SV SV% SPI Safe Guard Project -$31,530.42 -7% 0.93 Initiation $0.00 0% 1 Project Kick-off

Please interpret....Earned Value Cost Indicators: Cost Performance Index

Task Name SV SV% SPI
Safe Guard Project -$31,530.42 -7% 0.93
Initiation $0.00 0% 1
Project Kick-off with client $0.00 0% 1
Defining Scope & Develop a Project Charter $0.00 0% 1
Identify stakeholders and Project team $0.00 0% 1
Project charter sign-off $0.00 0% 0
Planning -$10,356.84 -35% 0.65
Business requirement gathering -$148.00 -5% 0.95
Preparing BRD (Business Requirement Document) -$96.00 -10% 0.9
Feedback/Changes on BRD from client -$59.14 -20% 0.8
Prepare SRS (System Requirement Specification) document -$195.00 -25% 0.75
Feedback/Changes on SRS from client -$243.50 -32% 0.68
Finalizing of BRD & SRS -$151.20 -28% 0.72
BRD & SRS sign-off -$9,464.00 -40% 0.6
BRD and SRS Sign-off complete $0.00 0% 0
Execution and Control -$21,173.58 -5% 0.95
Prioritze the use cases with the Product Owner -$2,232.30 -40% 0.6
Create sprints and acceptance criteria for each use case -$210.00 -5% 0.95
Product backlog finish. Sprint creation finish $0.00 0% 0
Develop the cyber-incident form, data breach form, membership form and software to protect data. Receive constant feedback from client for correction in each sprint review meeting -$18,731.27 -4% 0.96

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!