Question: Please interpret....Schedule Variance and Schedule Performance Variance Task Name SV SV% SPI Safe Guard Project -$31,530.42 -7% 0.93 Initiation $0.00 0% 1 Project Kick-off with
Please interpret....Schedule Variance and Schedule Performance Variance
| Task Name | SV | SV% | SPI |
| Safe Guard Project | -$31,530.42 | -7% | 0.93 |
| Initiation | $0.00 | 0% | 1 |
| Project Kick-off with client | $0.00 | 0% | 1 |
| Defining Scope & Develop a Project Charter | $0.00 | 0% | 1 |
| Identify stakeholders and Project team | $0.00 | 0% | 1 |
| Project charter sign-off | $0.00 | 0% | 0 |
| Planning | -$10,356.84 | -35% | 0.65 |
| Business requirement gathering | -$148.00 | -5% | 0.95 |
| Preparing BRD (Business Requirement Document) | -$96.00 | -10% | 0.9 |
| Feedback/Changes on BRD from client | -$59.14 | -20% | 0.8 |
| Prepare SRS (System Requirement Specification) document | -$195.00 | -25% | 0.75 |
| Feedback/Changes on SRS from client | -$243.50 | -32% | 0.68 |
| Finalizing of BRD & SRS | -$151.20 | -28% | 0.72 |
| BRD & SRS sign-off | -$9,464.00 | -40% | 0.6 |
| BRD and SRS Sign-off complete | $0.00 | 0% | 0 |
| Execution and Control | -$21,173.58 | -5% | 0.95 |
| Prioritze the use cases with the Product Owner | -$2,232.30 | -40% | 0.6 |
| Create sprints and acceptance criteria for each use case | -$210.00 | -5% | 0.95 |
| Product backlog finish. Sprint creation finish | $0.00 | 0% | 0 |
| Develop the cyber-incident form, data breach form, membership form and software to protect data. Receive constant feedback from client for correction in each sprint review meeting | -$18,731.27 | -4% | 0.96 |
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock