Question: please let me know the answer Question 8 (1 point) Saved Find the earliest start time (ES) of the activity D in the following network:

please let me know the answer
please let me know the answer Question 8 (1
Question 8 (1 point) Saved Find the earliest start time (ES) of the activity D in the following network: Activity Predecessor Time A 8 B 3 A 7 D AB 4 E C D 2