We are now part way through a project at a point where we had planned to have 73% of the work done. We have spent $309,237 of the total budget of $703,375. We have completed 76% of the activities. What is the ETC? (pick closest answer) A. $168,81 B. $309,237 C. $703,375 D. $478,047