Question: We are now part way through a project at a point where we had planned to have 73% of the work done. We have spent
We are now part way through a project at a point where we had planned to have 73% of the work done. We have spent $309,237 of the total budget of $703,375. We have completed 76% of the activities. What is the CPI? (pick closest answer) A. 1.17 B. 1.73 C. 1.44 D. 0.14