Question: QUESTION 1 We are now part way through a project at a point where we had planned to have 6 7 % of the work

QUESTION 1
We are now part way through a project at a point where we had planned to have 67% of the work done. We have spent $324,008 of the total budget of $886,285. We have completed 51% of the activities. What is the EV?(pick closest answer)
$324,008
$452,005
$593,811
$886,285