Question: Please solve quickly without explanation ... within 15 minutes 29 Sub-component J has a one week lead time and a gross requirement of 57 units


Please solve quickly without explanation ... within 15 minutes
29 Sub-component J has a one week lead time and a gross requirement of 57 units in Week 6 to fill order 123. There are already 15 J's in stock at the beginning of the planning period and these are not needed for any other order other than 123. What should the planned order release for J's be in Week 5? ed out of Select one: 9 question a. 57 b. 27 c. 72 d. 42 30 Which of the following cost is associated with inventories? out of Select one: a. Carrying cost b. Ordering cost c. Over stocking cost d. all of the aboveStep by Step Solution