Question: Subcomponent J has a one week lead time and a gross requirement of 5 7 units in Week 6 to fill order 1 2 3
Subcomponent J has a one week lead time and a gross requirement of units in Week to fill order There are already Js in stock at the beginning of the planning period and these are not needed for any other order other than What should be the planned order release for Js in order to build product at the latest possible completion time?
Question options:
A
units in week
B
units in week
C
units in week
D
units in week