Question: Subcomponent J has a one week lead time and a gross requirement of 5 7 units in Week 6 to fill order 1 2 3

Subcomponent J has a one week lead time and a gross requirement of 57 units in Week 6 to fill order 123. There are already 15 J's in stock at the beginning of the planning period and these are not needed for any other order other than 123. What should be the planned order release for J's in order to build product at the latest possible completion time?
Question 22 options:
A)
42 units in week 6
B)
57 units in week 5
C)
42 units in week 5
D)
57 units in week 6