Question: Sub-component J has a one week lead time and a gross requirement of 57 units in Week 6 to fill order 123. There are already

Sub-component J has a one week lead time and aSub-component J has a one week lead time and a

Sub-component J has a one week lead time and a gross requirement of 57 units in Week 6 to fill order 123. There are already 15 J's in stock at the beginning of the planning period and these are not needed for any other order other than 123. What are the gross requirements for J's in week 6? Select one: a. 57 units b. 42 units c. 92 units d. 22 units The planning horizon for a sales and operations plan is typically : Select one: a. 18-36 months O b. 3-18 months C. 36 - 60 months d. 0-3 months