Question 3: 1. Develop a network diagram based on the below data 2. How many paths do we have in our diagram? 3. Which path is our Critical Path? 4. Map out your Forward & Backward Pass. 5. Calculate the Float for each task. Duration (Days) Preceding Activity NO Activity Start (Milestone) Task A Task B Task C Task D Task E Task F Task G Task H Taski Finish ( Milestones) 2 5 3 4. 4. 6. 1 8. 2 0 Start Task A Task B and F Task C and I Start Task E Start Task G Task H Task D