Question: Please work at table for period 4 & 8 cost variance, schedule variance and cumulative EV and cumulative cost variance, schedule cost variance, Given the


Please work at table for period 4 & 8 cost variance, schedule variance and cumulative EV and cumulative cost variance, schedule cost variance,
Given the project baseline information given below, answer the following questions regarding variances in periods 4 and 8. Project Baseline Task 13 5 ES 16 17 8 19 10 11 13 14 12 15 SL 0 IN 1 250 2 250 0 - A B 0 750 750 Dur 2 6 5 4 3 3 250 250 600 1.200 1.500 Budget (PV) 500 3,000 4,500 800 450 1.800 750 300 250 900 B 9 12 12 200 2 2. 8 7 12 200 2 0 2 0 200 200 D E F 200 100 150 600 300 900 15 At the end of period 4: Percent Task Complete AC A 100% 450 B 60% 1,500 C 45%2.200 D 0% 0 E 0% 0 F 0% 0 At the end of period 8: At the end of period 8: Percent Task Complete AC A 100% 450 B 100% 3,200 100% 4,400 D 25% 150 E 33% 500 F 0% OStep by Step Solution