Question: please work out in detailed Problem Description: 1) Develop an PDM network for Project 1 (30 points) and Project 2 (30 points). Project 1 Project

please work out in detailed
Problem Description: 1) Develop an PDM network for Project 1 (30 points) and Project 2 (30 points). Project 1 Project 2 Activity Successor Relationship Activity B, C F-S (both) B D, E F-S E F-S B F-S E F F-S F Successor B C odotus IT WOUD Relationship F-S S-S F-S F -F 2) Given the PDM and activity data below, complete the PERT schedule calculation to fill out the empty cells. Also, clearly present your solution in the designated place no solution, no credit. Use the table below to put your answers. (40 points) PDM Activity Te Tm To Te SD V A 10 9 7. B 5 3 2 B D C 8 6 4 A F DI 9 6 5 E 5 4 2 E F 4 3 2 Project Put your solution hereStep by Step Solution