Question: pleass show work solving provlem three, below are examples of another problem Time Cost Example 3 Determine the project's cost and duration alternatives. Times (durations)

pleass show work solving provlem three, below are pleass show work solving provlem three, below are examples of another problem
pleass show work solving provlem three, below are
pleass show work solving provlem three, below are
pleass show work solving provlem three, below are
pleass show work solving provlem three, below are
pleass show work solving provlem three, below are
Time Cost Example 3 Determine the project's cost and duration alternatives. Times (durations) are in weeks and costs in $Ks. Perform three cycles of the process: determine the crash design, the normal design, and the next two designs (a total of 4 project designs). Activity Code NTCT NCCC Prec. Design setup D 12 8 200 400 . Technology setup T 9 6 260 360 . Equipment setup E 10 9 100 110 . Validation V 4 3 900 1,000 D, T, E Main Rollout M 11 9 360 440 V Protocols P 10 6 120 200 V PM Problem (Excercise 4). Determine the project's cost and duration alternatives. Times (durations) in days, costs in $K. Perform three cycles of the process: determine the crash design, the normal design, and the next two designs (a total of 4 project designs). Code NT CC Prec. 100 B, C mo 000 B, C Provide your answer in the following format 1. Crash design duration and cost: (d, $m) 2. Normal design duration and cost: (d, $m) 3. Normal design critical path: X-Y-Z 4. What activity (ies) will be crashed in this iteration: Y 5. First crash duration and cost: (d, $m) 6. First crash critical path (s): X-Y-Z; R-C-V 7. What activity(ies) will be crashed in this iteration: Y, C 8. Second crash duration and cost: (d, $m) This is how your answer (what you will type into Canvas) should look like (this is Exercise 4 in the Problem set): 1.(36,$679) Time Cost Example 4 Determine the project's cost and duration alternatives. Perform three cycles of the process: determine the crash design, the normal design, and the next two designs (a total of 4 project designs). Times in days, costs in $K. Code Prec. Rate NT 19 c F G 3 Sum NC =345) SUM CC = (679) All crash B 110 22 D 22 26 D TO 10 I 16 36 Duration loto 49 30 1722 30 36 Cost 679 Normal | A 10 12 112 10 12 S=0 B 12 28 11329 S8=1 1221 B19 112 21 28 37 G 3740 29 30 273 38 41 SD = 1 So=1 JE/21 41 ( Duration 20/21 41) Soro CP: A-C-E IF 28 361 Cost = 345 Sp=5 Scoo 18 33 41 Crash C Alternatives Crash C Crash A 25 13 lost increases + 345 Now 352 new Duration 41-1 = 40 crashiNG no a B 112 28 5 2937_ JG37 40 40 112 20 0112 20 116/12 28 19/28 371 11210 12 Se=0 SD-O SAO F 20 40 2020 401 Sr: F129 36 1832 40) Sf = 4 Alternatives Crash A (in both) 25 Crash B&C 7.5+ 13 = 20.5 Crash DAC 24 +13=37 Crash Gec 40 +13=53 cert 345 Soo Duration 40 CP: AC-E A-B-D-G Crash Crash Crash C Crash A 25 40 Alternatives crash C 13 lost increases + 345 new Duration Now I 350l crashiNG 41-1 = 40 NO S AB 12 28 L JD 2037 G137.40|| AIO 12 116/12 28 928 371 112 10 12 Se=0 SD- Soo SAO 12 20 E 20 40 Duration 120/20 401 Spo 40 F2936 CP: A-CE 1832 40) A-B-D-G Sp=4 Alternatives Crash A (in both) 25 Crash Crash B&C 7.5+ 13 = 20.5 Crash DAC 24 +13=37 Crash Gec 40 +13=53 345 112 20 Crash 1832 (crashino ( 41-1=40 B/ 12 28 A0 2 16 12 28 G37 40 92837 7 9/28 37 11210 12 3 3740 So=0 SAO WC 12 20 E 20 40 18 12 20 120/20 40 Duration SEO 40 +28 36 CP. ACE A-B-D-G Sp=4 Alternatives Crash A (in both) 25 Crash Crash Bec7.5+13=20.5 Crash DEC 24 +13=37 Crash Gece 40+13=53 Cost increases to 345 82 ses to 13 C crashin c) SUMMARY 20.5 (crashing BSC 41 (normal) $ 345 New Cost = 378.5 40 (crash c) $ 359 New Duration=39 39 (cras BLC) 5379.5 36 (all crash) $679

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!