Question: pls help out with this Activity IP A B D E F G I A A B, C A E D, F Mean 2 5

pls help out with this
Activity IP A B D E F G I A A B, C A E D, F Mean 2 5 3 5 2 3 IP: Immediately Preceding Activity Mean: Expected Time in weeks CT: Crash time in weeks CT 2 3 2 3 1 3 4 C/W N/A $800 $700 $750 $400 N/A $1,000 C/W: Crash cost per week 1. The latest start time for activity D is x 5 2. If the manager does not want to start activity A immediately, how long could he wait before starting this activity and still meet a deadline of 21 weeks? Activity IP A B D E F G I A A B, C A E D, F Mean 2 5 3 5 2 3 IP: Immediately Preceding Activity Mean: Expected Time in weeks CT: Crash time in weeks CT 2 3 2 3 1 3 4 C/W N/A $800 $700 $750 $400 N/A $1,000 C/W: Crash cost per week 1. The latest start time for activity D is x 5 2. If the manager does not want to start activity A immediately, how long could he wait before starting this activity and still meet a deadline of 21 weeks
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts