Question: Polycorp is considering a new project. The project has beta (B) that is twice that of the firm's existing assets (projects). Polycorp's existing assets
Polycorp is considering a new project. The project has beta (B) that is twice that of the firm's existing assets (projects). Polycorp's existing assets have a required return (cost of capital) of 9%, the market risk premium is 7% and the risk free rate is 4%. Calculate the beta for the new project. Provide your answer accurate to two decimal places.
Step by Step Solution
3.42 Rating (155 Votes )
There are 3 Steps involved in it
We can use the following formula to calculate the required return of th... View full answer