Question: Preceding Time left 0:19:11 Activity Duration 9 B A 2 A 12 D A 5 E B 6 F B A network consists of 8

Preceding Time left 0:19:11 Activity Duration 9 B
Preceding Time left 0:19:11 Activity Duration 9 B A 2 A 12 D A 5 E B 6 F B A network consists of 8 G CF 3 H D 2 I H 8 J GI 6 K EJ 2 the following list. Times are given in weeks. How many critical paths are there? Select one: O a zero critical path b. 1 critical path c. 2 critical paths Od 3 critical paths