Question: Problem 1 5 - 6 ( Static ) Consider the following information about a small project: Task Duration Estimates Immediate Predecessors A 2 days None
Problem Static
Consider the following information about a small project:
Task Duration Estimates Immediate Predecessors
A days None
B days A
C day B
D days A
E days B and D
F days E and C
Click here for the Excel Data File
b Identify the critical path.
b Identify the earliest start and finish.
b Identify the slack for each task.
c Which of these activities should the project manager track most closely?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
