Question: Problem 1 5 - 6 ( Static ) Consider the following information about a small project: Task Duration Estimates Immediate Predecessors A 2 days None

Problem 15-6(Static)
Consider the following information about a small project:
Task Duration Estimates Immediate Predecessors
A 2 days None
B 5 days A
C 1 day B
D 2 days A
E 3 days B and D
F 12 days E and C
Click here for the Excel Data File
b-1. Identify the critical path.
b-2. Identify the earliest start and finish.
b-3. Identify the slack for each task.
c. Which of these activities should the project manager track most closely?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!