Question: Problem 1 Consider the following project table: table [ [ Activity , table [ [ Immediate ] , [ Predecessors ] ] ,

Problem 1
Consider the following project table:
\table[[Activity,\table[[Immediate],[Predecessors]],m (weeks),a (weeks),b (weeks)],[A,-,5,2,8],[B,-,5,1,9],[C,A,6,4,9],[D,B,2,2,2],[E,A,2,1,9],[F,C, D,4,2,5],[G,C, E,8,3,10],[H,F, G,2,1,3]]
What is the probability that the project can be completed in 19 weeks? Please provide an explanation for your answer.
 Problem 1 Consider the following project table: \table[[Activity,\table[[Immediate],[Predecessors]],m (weeks),a (weeks),b (weeks)],[A,-,5,2,8],[B,-,5,1,9],[C,A,6,4,9],[D,B,2,2,2],[E,A,2,1,9],[F,C,