Question: Problem 1 - CPM: Consider the following network diagram for a project (the times shown are in weeks): 7 H 8 8 5 3 End

Problem 1 - CPM: Consider the following network

Problem 1 - CPM: Consider the following network diagram for a project (the times shown are in weeks): 7 H 8 8 5 3 End Start 3 G B 2 10 E 7 a (a) Do a forward/backwards pass. Identify the slack for each activity and identify the critical path. (b) How long will it take to complete this project? (c) Can activity D be delayed without delaying the entire project? If so, how many weeks? (d) Can activity C be delayed without delaying the entire project? If so, how many weeks? (e) What is the schedule for activity E (i.e., ES, EF, LS, LF)