Question: Problem 1: Given the following. Crash Time (days) Crashed Cost (total) Normal Time (days) 7 Normal Cost $500 4 $800 Activity A: Obtain instructor B:

Problem 1: Given the following. Crash Time (days)

Problem 1: Given the following. Crash Time (days) Crashed Cost (total) Normal Time (days) 7 Normal Cost $500 4 $800 Activity A: Obtain instructor B: Locate a room C: Check costs D: Room open? E: Schedule class 2 4 1 1 350 900 500 550 $3100 3 6 3 2 200 500 200 300 a) Find the crash cost per day. b) Which activities should be crashed to meet a project deadline of 10 days with a minimum cost? Assume partial crashing. c) Find the new cost. d) Is partial crashing an appropriate assumption in this kind of project