Question: Problem 1 penalty costs are $ 1 , 4 0 0 per week after week 1 2 . table [ [ Activity Immediate Predecessor

Problem 1 penalty costs are $1,400 per week after week 12.
\table[[Activity Immediate Predecessor(s),Normal Time (weeks),\table[[Crash],[Time (weeks)]],\table[[Normal],[Cost ($)]],\table[[Crash],[Cost ($)]],],[A,-,4,1,5,500,8,000],[B,-,5,3,7,500,10,000],[C,A,1,1,4,000,4,000],[D,B,6,3,5,500,12,500],[E,B, C,7,6,4,500,6,500],[F,D,7,6,3,500,7,000]]
a. What is the minimum-cost schedule for this project?
The minimum-cost schedule is weeks. (Enter your response as an integer.)
 Problem 1 penalty costs are $1,400 per week after week 12.