Question: Problem 2 Calculate the normal, least - cost , and crash durations for the following project. Calculate the cost associated with each duration. Indirect (

Problem 2
Calculate the normal, least-cost, and crash durations for the following project. Calculate the cost associated with each duration. Indirect (overhead) costs are $100 per day.
\table[[,,Duration (Days),Cost ($)],[Activity,IPA,Normal,Crash,Normal Crash],[A,-,7,5,500,660],[B,-,3,2,660,725],[C,-,8,5,800,975],[D,A,B,4,3,1000,1125],[E,B,C,11,9,600,750],[F,D,6,3,560,600],[G,F,4,2,700,900],[H,E,G,3,2,1000,1200],[I,H,2,2,300,300]]