Question: Problem 3 : An end product is being produced in a large manufacturing plant. The bill of material diagram is as follows: The lead time

Problem 3:
An end product is being produced in a large manufacturing plant. The bill of material diagram is as follows:
The lead time is given in weeks.
The MPS schedule for this end product for the following four weeks, ten weeks from now is as follows:
\table[[Week 10,Week 11,Week 12,Week 13],[10,14,19,9]]
The fixed order cost is $100 for all the units, and the holding cost is $0.6unit/week for all the units.
a) Assuming the silver meal lot production for all the components, determine the planned order releases for component P.
b) Suppose the production capacity for item C is 55 units per week. If we start producing at week 8, is it possible to find a planned order release without backordering? If backordering is allowed at a cost of $5 unit/item, formulate a mathematical program that minimize the total cost from item C.
 Problem 3: An end product is being produced in a large

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!