Question: Problem 4 - 7 ( Static ) The following activities are part of a project to be scheduled using CPM: table [ [ ACTIVITY

Problem 4-7(Static)
The following activities are part of a project to be scheduled using CPM:
\table[[ACTIVITY,IMMEDIATE PREDECESSOR,TIME (WEEKS)],[A,,6],[B,A,3],[C,A,7],[D,C,2],[E,B, D,4],[F,D,3],[G,E,F,7]]
b. What is the critical path?
A-C-D-F-G
A-C-D-E-G
A-B-E-G
c. How many weeks will it take to complete the project?
Number of weeks
d. How much slack does activity B have?
Slack of activity B
weeks