Question: Problem 4 - 7 ( Static ) The following activities are part of a project to be scheduled using CPM: table [ [ ACTIVITY
Problem Static
The following activities are part of a project to be scheduled using CPM:
tableACTIVITYIMMEDIATE PREDECESSOR,TIME WEEKSABACADCEB DFDG
b What is the critical path?
ACDFG
ACDEG
ABEG
c How many weeks will it take to complete the project?
Number of weeks
d How much slack does activity B have?
Slack of activity B
weeks
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
