Question: Problem 5 - 8 ( Algo ) Schedule the following activities using CPM: b . What is the critical path? A - B - D

Problem 5-8(Algo)
Schedule the following activities using CPM:
b. What is the critical path?
A-B-D-F-G-H
A-C-E-H
A-B-D-E-H
A-C-E-F-G-H
c. How many weeks will it take to complete the project?
Number of weeks
d. Which activities have slack, and how much?
A,1 week; B,2 weeks; D,4 weeks.
B,3 weeks; D,2 weeks; E,4 weeks.
C,3 weeks; F,1 week; G,1 week.