Question: Problem 5-8 (Algo) Schedule the following activities using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A 5 B A 3 C A 4 D B 6

Problem 5-8 (Algo)

Schedule the following activities using CPM:

ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS)
A 5
B A 3
C A 4
D B 6
E C

D
8
F D 2
G F 4
H E

G
3

b. What is the critical path?

multiple choice 1

  • A-C-E-F-G-H

  • A-B-D-F-G-H

  • A-B-D-E-H

  • A-C-E-H

c. How many weeks will it take to complete the project?