Question: Problem 5 Using the following project information, calculate the expected time for each of the project activities. Activity Optimistic Time Estimate(weeks) Most Likely Time Estimates

Problem 5

Using the following project information, calculate the expected time for each of the project activities.

Activity Optimistic Time Estimate(weeks) Most Likely Time Estimates (weeks) Pessimistic Time Estimates (weeks) Immediate Predecessor(s)
A 2 6 9 none
B 4 6 7 A
C 4 7 12 A
D 5 5 10 B
E 6 11 17 C
F 4 5 5 D,E
G 4 5 10 D,E
H 4 6 11 F
I 6 9 12 G
J 3 3 3 H,I

(Round your answers to 2 decimal places, the tolerance is +/-0.01)

Activity Expected Time
A
B
C
D
E
F
G
H
I
J

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Mathematics Questions!