Question: Using the following project information, calculate the variance for each of the project activities. Activity Optimistic Time Most Likely Time Pessimistic Time Immediate Estimate (weeks)

Using the following project information, calculate the variance for each of the project activities. Activity Optimistic Time Most Likely Time Pessimistic Time Immediate Estimate (weeks) Estimates (weeks) Estimates (weeks) Predecessor(s)
A 3 6 9 none
B 3 5 7 A
C 4 7 12 A
D 4 8 10 B
E 5 10 16 C
F 3 4 5 D, E
G 3 6 8 D, E
H 5 6 10 F
I 5 8 11 G
J 3 3 3 H, I
(Round your answers to 3 decimal places, the tolerance is +/-0.001.)
Activity Variance
A ______________
B _____________
C _______________
D _______________
E ____________
F _________________
G __________________
H _________________
I __________________
J ____________________

Step by Step Solution

3.38 Rating (164 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

The variance Tp To 62 where Tp is the time of pessimistic and To is the tim... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

1019-B-C-A-C-A(2469).docx

120 KBs Word File

Students Have Also Explored These Related Cost Accounting Questions!