Question: Problem 5-11 There is an 80% chance the project below can be completed in D weeks or less. ACTIVITY MOST OPTIMISTIC MOST LIKELY MOST PESSIMISTIC

Problem 5-11

There is an 80% chance the project below can be completed in D weeks or less.

Problem 5-11 There is an 80% chance the project

ACTIVITY MOST OPTIMISTIC MOST LIKELY MOST PESSIMISTIC
A 2 5 14
B 1 4 4
C 4 1 7
D 4 6 11
E 4 9 14

What is D? (Round your answer to the nearest whole number.)

D __________