Question: Problem 5-11 There is an 80% chance the project below can be completed in D weeks or less. ACTIVITY MOST OPTIMISTIC MOST LIKELY MOST PESSIMISTIC
Problem 5-11
There is an 80% chance the project below can be completed in D weeks or less.

| ACTIVITY | MOST OPTIMISTIC | MOST LIKELY | MOST PESSIMISTIC | |
| A | 2 | 5 | 14 | |
| B | 1 | 4 | 4 | |
| C | 4 | 1 | 7 | |
| D | 4 | 6 | 11 | |
| E | 4 | 9 | 14 | |
What is D? (Round your answer to the nearest whole number.)
D __________
D EStep by Step Solution
There are 3 Steps involved in it