Question: There is an 82% chance the project below can be completed in D weeks or less. B D A E MOST ACTIVITY OPTIMISTIC 1 B

There is an 82% chance the project below can be

There is an 82% chance the project below can be completed in D weeks or less. B D A E MOST ACTIVITY OPTIMISTIC 1 B 4 3 D 6 E 7 MOST LIKELY 6 5 1 11 7 MOST PESSIMISTIC 11 3 5 13 10 What is D? (Round your answer to the nearest whole number.) D

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!