Question: Problem 7 Assembling a device requires 13 tasks. The tasks, precedence relationship and task times are given in the table below. Given a productive working

Problem 7 Assembling a device requires 13 tasks.

Problem 7 Assembling a device requires 13 tasks. The tasks, precedence relationship and task times are given in the table below. Given a productive working time of 8 hours per day, and a requirement to produce 48 units per day, A) Determine the cycle time B) Draw a precedence diagram C) Compute the minimum number of workstations required to balance the assembly line Immediate Predecesso Task Time (Minutes) Task None 3 3 3 D B F D G TC,E,F HG KH M IKAL Total 68