Question: Processing time (minutes per toy) 10 10 Activity Cutting Sewing Stuffing Assembling Packaging 5 25 Demand rate is 4 toys per hour. Currently we have

Processing time (minutes per toy) 10 10 Activity

Processing time (minutes per toy) 10 10 Activity Cutting Sewing Stuffing Assembling Packaging 5 25 Demand rate is 4 toys per hour. Currently we have worker A in charge of cutting, worker B in charge of sewing and stuffing, and worker C in charge of assembling and packaging. Which of the following strategies will increase the process capacity by balancing the line? Multiple Choice o o Adding one additional worker to assembling. C) Adding two additional workers to assembling. o Moving packaging to worker A