Question: Project ABC Scope = 10 chairs @ $10.00 = $100.00 PV = $50 Timeframe = 10 days AC = $44 At the End of the

Project ABC Scope = 10 chairs @ $10.00 = $100.00 PV = $50 Timeframe = 10 days AC = $44 At the End of the 5" day 4 chairs were = 40% EV =$40 Completed at a cost of $11.00 each = CV = -4 (over budget) CPI= 0.91 SV = -10 SPI= 0.8 CR = $110 /12days