Question: Project ABC Scope = 10 chairs @ $10.00 = $100.00 Timeframe = 10 days At the End of the 5 th day 4 chairs were
Project ABC
Scope = 10 chairs @ $10.00 = $100.00
| Timeframe = 10 days |
| At the End of the 5th day 4 chairs were |
| Completed at a cost of $11.00 each
Find
|
| PV = |
| AC = |
| EV = |
| CV = |
| CPI= SV = |
| SPI= |
| CR = |
Step by Step Solution
There are 3 Steps involved in it