Question: Project ABC Scope = 10 chairs @ $10.00 = $100.00 Timeframe = 10 days At the End of the 5 th day 4 chairs were

Project ABC

Scope = 10 chairs @ $10.00 = $100.00

Timeframe = 10 days

At the End of the 5th day 4 chairs were

Completed at a cost of $11.00 each

Find

PV =

AC =

EV =

CV =

CPI=

SV =

SPI=

CR =