Question: 3. value: 10.00 points Project management (2) Consider the following project: Activity Immediate Predecessors Durations (weeks) 3 A B A 3 c A 2 D

3. value: 10.00 points Project management (2)
3. value: 10.00 points Project management (2) Consider the following project: Activity Immediate Predecessors Durations (weeks) 3 A B A 3 c A 2 D B 3 E Z F . DE 3 G 6 H 2 Which activity is not a critical activity? B