Question: Project management (3) Consider the following project: Activity Immediate Predecessors Durations (weeks) A 5 B A 3 A 2 D 3 E 7 F 3

Project management (3) Consider the following

Project management (3) Consider the following project: Activity Immediate Predecessors Durations (weeks) A 5 B A 3 A 2 D 3 E 7 F 3 B,C D, E G 6 H 2 Which one of the following would expedite the project? Expediting H by 1 week Expediting F by 1 week Expediting D by 1 week Expediting G by 1 week