Question: Given the information below: Activity Immediate Predecessors Duration (days) A - 5 B - 6 C - 3 D C 2 E A 5 F

Given the information below:

Activity Immediate Predecessors Duration (days)
A - 5
B - 6
C - 3
D C 2
E A 5
F B, D 10
G C 7

A. PROJECT COMPLETION IN DAYS: _____

B. IS TASK A CRITICAL? Y OR N

C. TASK B HAS A TOTAL FLOAT OF ___ DAYS

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!