Question: project management Below is the information on a small project. All information is in days and the crash time is the amount of time that
project management
Below is the information on a small project. All information is in days and the crash time is the amount of time that the project can be shortened along with the associated cost of crashing. Hint: In order to be successful in this activity you must draw out the AON diagram on your own in order to best answer the following questions. 1 Identify the critical path. 2. What is the expected project length? 3. Identify the slack in the project ie. What activity and how many days? 4. Indicate ES/EF/LS/LF at activity "L" on your network diagram? 5. What is the most economical way to reduce the project time (crash) by 2 days? Blank # 1
Step by Step Solution
There are 3 Steps involved in it